South Carolina
We care about your money as much as you do!
in under 5 minutes
Pricing starts at $18* | See pricing options
We care about your money as much as you do!
Though not strictly required by South Carolina law, it is the best business practice to file a Notice of Project Commencement (NOC) within 15 days of starting any new residential project. An NOC protects a general contractor from excessive lower-tier liens. The notice forces a lower-tier subcontractor or supplier to respond with a Notice of Furnishing to have full lien rights.
A Notice of Claim of Lien must be sent by the contractor within 90 days of last furnishing of labor or materials to the project residential project in South Carolina.
If you do not have a direct contract with the owner as a subcontractor, it is very important to send a Notice of Furnishing Labor or Materials (NOF) at the start of the South Carolina project. While sending an NOF is not legally required, this notice can secure your right to a Full Price Lien in the event that a Notice of Commencement is recorded by the general contractor for the residential project. Without a Notice of Furnishing Labor or Materials, you may only be entitled to a lien on the balance remaining to the general contractor. If you are second-tier or lower, this is the only way to secure full lien rights.
A Notice of Claim of Lien must be sent by the subcontractor within 90 days of last furnishing of labor or materials to the residential project in South Carolina.
If you do not have a direct contract with the owner as a supplier, it is very important to send a Notice of Furnishing Labor or Materials (NOF) at the start of the South Carolina residential project. While sending an NOF is not legally required, this notice can secure your right to a Full Price Lien in the event that a Notice of Commencement is recorded by the general contractor. Without a Notice of Furnishing Labor or Materials, you may only be entitled to a lien on the balance remaining to the General Contractor. If you are second tier or lower, this is the only way to secure full lien rights.
A Notice of Claim of Lien must be sent by the supplier within 90 days of last furnishing of labor or materials to the residential project in South Carolina.
Though not strictly required by the law, it is best business practice to file a Notice of Project Commencement (NOC) within 15 days of starting any new commercial project in South Carolina. An NOC protects a general contractor from excessive lower tier-liens. The notice forces a lower-tier subcontractor or supplier to respond with a Notice of Furnishing to have full lien rights.
A Notice of Claim of Lien must be sent by the general contractor within 90 days of last furnishing of labor or materials to the South Carolina commercial project.
If you as a subcontractor do not have a direct contract with the owner, it is very important to send a Notice of Furnishing Labor or Materials (NOF) at the start of the commercial project. While sending an NOF is not legally required, this notice can secure your right to a Full Price Lien in the event that a Notice of Commencement is recorded by the South Carolina general contractor. Without a Notice of Furnishing Labor or Materials, you may only be entitled to a lien on the balance remaining to the general contractor. If you are second-tier or lower, this is the only way to secure full lien rights.
A Notice of Claim of Lien must be sent by the subcontractor within 90 days of last furnishing of labor or materials to the South Carolina commercial project.
If you do not have a direct contract with the owner, it is very important for you as a supplier to send a Notice of Furnishing Labor or Materials (NOF) at the start of the South Carolina commercial project. While sending an NOF is not legally required, this notice can secure your right to a Full Price Lien in the event that a Notice of Commencement is recorded by the general contractor. Without a Notice of Furnishing Labor or Materials, you may only be entitled to a lien on the balance remaining to the general contractor. If you are second-tier or lower, this is the only way to secure full lien rights.
Suppliers in South Carolina need to send a Notice of Claim of Lien within 90 days of last furnishing of labor or materials to the commercial project.
There are no formal requirements for subcontractors working on state projects in South Carolina. But best business practice is to send a Preliminary Notice to inform all parties that you have furnished material to the project.
A Claim on Bond should be sent by the subcontractor on the state project within 90 days of last furnishing of labor or materials to the South Carolina project.
Although it is not a legal requirement to send a Preliminary Notice as a supplier, it is best practice to do so in South Carolina. Sending this notice advises all parties that you are working on the state project and helps you get paid faster.
The supplier must send a Claim on Bond within 90 days of the supplier last furnishing labor or materials to the state project in South Carolina.
Not applicable, a contractor cannot take action on their own bond.
Not applicable, a contractor cannot take action on their own bond.
Although it is not a legal requirement to send a preliminary notice for federal projects, it is best practice for subcontractors to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
Though sending a preliminary notice it is not strictly required, the best business practice is to send it anyway. The preliminary notice makes it more likely that you will be paid on time and lets the General Contractor know you are serious about getting paid.
A Miller Act Notice needs to be sent by subcontractors in 90 days from last furnishing of labor and/or materials to the federal project.
Claim on bond must be filed within 90 days of last furnishing of labor or materials.
Although it is not a legal requirement to send a preliminary notice, it is best practice to do so for federal projects. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
Though sending a preliminary notice it is not strictly required, the best business practice is to send it anyway. The preliminary notice makes it more likely that you will be paid on time and lets the General Contractor know you are serious about getting paid.
A Miller Act Notice is required to be sent by the supplier 90 days from last furnishing of labor and/or materials to the federal project.
Claim on bond must be filed within 90 days of last furnishing of labor or materials.
Download South Carolina preliminary notice, mechanics lien and construction bond claim ebooks and other printable resources
Download South Carolina preliminary notice, mechanics lien and construction bond claim infographics
Watch and learn from the best of South Carolina preliminary notice, mechanics lien and construction bond claim videos by SunRay
We have a rich collection of webinar videos that you can stream. Also you can register for our upcoming webinars for free
Stay updated with our blog articles on preliminary notice, notice of intent to lien, mechanic's lien and claim on bond. We cover every update in the lien law in all the 50 states. Subscribe to our newsletter to receive all our updates