Although it is not a legal requirement to send a Preliminary Notice, it is best practice to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
A Lien Statement must be sent 4 months from the last furnishing of labor and/or materials.
A Notice to Owner must be sent by Oklahoma subcontractors on owner-occupied residential properties at the start of work to inform the owners of the possibility of a lien.
A pre-lien notice must be sent within 75 days from last furnishing labor and/or materials.
A Lien Statement must be sent by the subcontractor to the Kansas commercial job, 90 days from the last furnishing of labor and/or materials.
A Notice to Owner must be sent on owner-occupied residential properties at the start of work by the supplier to inform the owners of the possibility of a lien on their residential project in Oklahoma.
A pre-lien notice must be sent within 75 days from last furnishing labor and/or materials to the residential project.
A Lien Statement must be sent 90 days from the supplier last furnishing labor and/or materials to the residential project in Oklahoma.
Although it is not a legal requirement to send a Preliminary Notice, it is best practice to do so as a general contractor. Sending a Preliminary Notice advises all parties that you are working on the Oklahoma commercial project and helps you get paid faster.
A Lien Statement must be sent by the general contractor to the Oklahoma commercial job 4 months from the last furnishing of labor and/or materials.
Although it is not a legal requirement to send a Preliminary Notice, it is best practice to do so. Sending a Preliminary Notice advises all parties that you are working on the commercial project and helps you get paid faster as a subcontractor in Oklahoma.
A pre-lien notice must be sent within 75 days from last furnishing labor and/or materials.
A Lien Statement must be sent 90 days from the subcontractor last furnishing of labor and/or materials to the commercial job.
Although it is not a legal requirement to send an Oklahoma Preliminary Notice, it is best practice to do so as a supplier to a commercial job. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.
A pre-lien notice must be sent within 75 days from last furnishing labor and/or materials to the Oklahoma job by the supplier.
A supplier must send a Lien Statement 90 days from the last furnishing of labor and/or materials to the commercial project in Oklahoma.
Although in Oklahoma it is not a legal requirement to send a Preliminary Notice for state jobs, it is best practice to do so as a subcontractor. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.
Subcontractors must send a Lien Statement 90 days from last furnishing labor and/or materials to a commercial project in Oklahoma.
Although it is not a legal requirement to send a Preliminary Notice in Oklahoma as a supplier, it is best practice to do so for commercial projects. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.
A Lien Statement must be sent by the supplier 90 days from last furnishing labor and/or materials to the Oklahoma commercial job.
Although it is not a legal requirement to send a preliminary notice for federal projects, it is best practice for subcontractors to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
A Miller Act Notice needs to be sent by subcontractors in 90 days from last furnishing of labor and/or materials to the federal project.
Although it is not a legal requirement to send a preliminary notice, it is best practice to do so for federal projects. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
A Miller Act Notice is required to be sent by the supplier 90 days from last furnishing of labor and/or materials to the federal project.
Download Oklahoma preliminary notice, mechanics lien and construction bond claim ebooks and other printable resources
Download Oklahoma preliminary notice, mechanics lien and construction bond claim infographics
Watch and learn from the best of Oklahoma preliminary notice, mechanics lien and construction bond claim videos by SunRay
We have a rich collection of webinar videos that you can stream. Also you can register for our upcoming webinars for free
Stay updated with our blog articles on preliminary notice, notice of intent to lien, mechanic's lien and claim on bond. We cover every update in the lien law in all the 50 states. Subscribe to our newsletter to receive all our updates