Although it is not a legal requirement to send a Preliminary Notice as a general contractor, it is the best business practice to do so for Ohio projects. Sending a notice advises all parties that you are working on the residential project and helps you get paid faster.
An Affidavit of Mechanic's Lien must be filed by the general contractor within 60 days of last furnishing labor or materials residential Ohio project.
A Notice of Furnishing is required for the subcontractor within 21 days of first furnishing labor and/or materials or from the date the Notice of Commencement is filed. You may request a Notice of Commencement by certified mail and the owner is required to send a copy within 10 days. If a Notice of Commencement is not filed, the subcontractor does not have to give a Notice of Furnishing for Ohio residential projects.
A Notice of Furnishing is required within 21 days of first furnishing labor and/or materials or from the date the Notice of Commencement is filed. You may request a Notice of Commencement by certified mail. The Ohio owner is put on notice and is required to send a copy within 10 days for residential projects in Ohio. If a Notice of Commencement is not filed, subcontractors do not have to give a Notice of Furnishing.
A subcontractor must file an Affidavit of Mechanic's Lien must within 60 days of last furnishing labor or materials to the Ohio residential project.
A Notice of Furnishing is required within 21 days of the supplier first furnishing labor and/or materials to the Ohio residential project or from the date the Notice of Commencement is filed. You may request a Notice of Commencement by certified mail. The owner is put on notice and is required to send a copy within 10 days. If a Notice of Commencement is not filed, suppliers do not have to give a Notice of Furnishing.
A Notice of Furnishing is required to be sent by the supplier within 21 days of first furnishing labor and/or materials to the Ohio residential job or from the date the Notice of Commencement is filed. You may request a Notice of Commencement by certified mail and the owner is required to send a copy within 10 days. If a Notice of Commencement is not filed, suppliers do not have to give a Notice of Furnishing.
A supplier must file a Affidavit of Mechanic's Lien within 60 days of last furnishing labor or materials to the Ohio residential project.
A Notice of Commencement is required to be sent by the general contractor at the start of work on the commercial project in Ohio. The NOC is recorded in the county where the work is being done.
Although it is not a legal requirement to send a Preliminary Notice, it is the best business practice to do so. Sending this notice as a contractor advises all parties that you are working on the project and helps you get paid faster.
An Affidavit of Mechanic's Lien must be filed by the general contractor 75 days from last furnishing labor and/or materials to the Ohio commercial project.
A Notice of Furnishing is required from the subcontractor within 21 days of first furnishing labor and/or materials to the Ohio commercial project or from the date the Notice of Commencement is filed. You may request a Notice of Commencement by certified mail and the owner is required to send a copy within 10 days. If a Notice of Commencement is not filed suppliers do not have to give a Notice of Furnishing.
A Notice of Furnishing is required in Ohio for commercial projects within 21 days of first furnishing labor and/or materials or from the date the Notice of Commencement is filed in Ohio. You may request a Notice of Commencement by certified mail. The owner is put on notice and is required to send a copy within 10 days. If a Notice of Commencement is not filed, subcontractors do not have to give a Notice of Furnishing.
An Affidavit of Mechanic's Lien should be sent by the subcontractor 75 days from last furnishing labor and/or materials to the Ohio commercial project.
A Notice of Furnishing is required from the supplier within 21 days of first furnishing labor and/or materials to the Ohio commercial job or from the date the Notice of Commencement is filed. You may request a Notice of Commencement by certified mail and the owner is required to send a copy within 10 days. If a Notice of Commencement is not filed the subcontractors and suppliers do not have to give a Notice of Furnishing.
A Notice of Furnishing is required to be sent by the Ohio supplier within 21 days of first furnishing labor and/or materials or from the date the Notice of Commencement is filed for the commercial projects. You may request a Notice of Commencement by certified mail. The owner is put on notice and is required to send a copy within 10 days. If a Notice of Commencement is not filed the subcontractors and suppliers do not have to give a Notice of Furnishing.
Suppliers must send an Affidavit of Mechanic's Lien in Ohio 75 days from last furnishing labor and/or materials to the commercial project.
A Notice of Furnishing is required within 21 days of first furnishing labor and/or materials or from the date the Notice of Commencement is filed for the Ohio state project. As a subcontractor you may request a Notice of Commencement by certified mail and the owner is required to send a copy within 10 days. If a Notice of Commencement is not filed the subcontractors and suppliers do not have to give a Notice of Furnishing.
A Claim on Bond must be made by the subcontractor within 90 days of last furnishing of labor and/or materials to the Ohio state project.
A Lien Upon Funds for public Ohio projects is a collection tool available to subcontractors when they do not get paid. This lien must be sent within 120 days of last furnishing material and/or labor.
A Notice of Furnishing is required within 21 days of first furnishing labor and/or materials by the supplier or from the date the Notice of Commencement is filed on the state job. You may request a Notice of Commencement by Ohio certified mail and the owner is required to send a copy within 10 days. If a Notice of Commencement is not filed the subcontractors and suppliers do not have to give a Notice of Furnishing.
Although it is not a legal requirement to send a Preliminary Notice, it is the best business practice to do so in Ohio. Sending this notice advises all parties that you as the supplier are working on the state project and helps you get paid faster.
A Claim on Bond must be made by the supplier within 90 days of last furnishing of labor and/or materials to the Ohio state project.
Although it is not a legal requirement to send a preliminary notice for federal projects, it is best practice for subcontractors to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
A Miller Act Notice needs to be sent by subcontractors in 90 days from last furnishing of labor and/or materials to the federal project.
Although it is not a legal requirement to send a preliminary notice, it is best practice to do so for federal projects. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
A Miller Act Notice is required to be sent by the supplier 90 days from last furnishing of labor and/or materials to the federal project.
Download Ohio preliminary notice, mechanics lien and construction bond claim ebooks and other printable resources
Download Ohio preliminary notice, mechanics lien and construction bond claim infographics
Watch and learn from the best of Ohio preliminary notice, mechanics lien and construction bond claim videos by SunRay
We have a rich collection of webinar videos that you can stream. Also you can register for our upcoming webinars for free
Stay updated with our blog articles on preliminary notice, notice of intent to lien, mechanic's lien and claim on bond. We cover every update in the lien law in all the 50 states. Subscribe to our newsletter to receive all our updates