District of Columbia
We care about your money as much as you do!
in under 5 minutes
Pricing starts at $18* | See pricing options
We care about your money as much as you do!
Although it is not a legal requirement to send a Preliminary Notice, it is best business practice to do so in the District of Columbia for residential projects. Sending a Preliminary Notice advises all parties that you as the general contractor are working on the project and helps you get paid faster.
A Lien Request must be filed by the general contractor in the District of Columbia no later than 90 days from the later date of either the completion or abandonment of the residential project.
Although it is not a legal requirement for a subcontractor to send a Preliminary Notice, it is best business practice to do so for residential projects. Sending a Preliminary Notice advises all parties that you are working on the District of Columbia project and helps you get paid faster.
The subcontractor must file a Lien Request no later than 90 days from the later date of either the completion or abandonment of the residential project in the District of Columbia.
Although it is not a legal requirement in the District of Columbia to send a Preliminary Notice, it is best business practice to do so. Sending a Preliminary Notice advises all parties that you are working on the project and helps you as a supplier, get paid faster.
A Lien Request must be filed by the supplier no later than 90 days from the later date of either the completion or abandonment of the residential project in the District of Columbia.
Although it is not a legal requirement to send a Preliminary Notice as a general contractor, it is the best business practice to do so in the District of Columbia. Sending a Preliminary Notice advises all parties that you are working on the commercial project and helps you get paid faster.
A Lien Request must be filed by the general contractor no later than 90 days from the later date of either the completion or abandonment of the commercial project in the District of Columbia.
Although it is not a legal requirement to send a Preliminary Notice, it is best business practice to do so as a subcontractor on a commercial job. Sending a Preliminary Notice advises all parties that you are working on the project in the District of Columbia and helps you get paid faster.
In the District of Columbia, a Lien Request must be filed by the subcontractor no later than 90 days from the later date of either the completion or abandonment of the project.
In the District of Columbia, although it is not a legal requirement to send a Preliminary Notice, it is best business practice to do so as a supplier. Sending a Preliminary Notice advises all parties that you are working on the commercial project and helps you get paid faster.
A Lien Request in the District of Columbia must be filed by the supplier no later than 90 days from the later date of either the completion or abandonment of the commercial project.
Although in the District of Columbia, it is not a legal requirement for a subcontractor to send a Preliminary Notice for public projects, it is best business practice to do so. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.
A Claim on Bond must be filed within 90 days of last furnishing of labor and/or materials for those who are not working directly with the general contractor on a state project. Though it is only required for those not contracted directly with the general contractor, it is the best business practice for any subcontractor to send one in the District of Columbia.
Although it is not a legal requirement to send a Preliminary Notice, it is best business practice to do so as a supplier on a public project in the District of Columbia. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.
A Claim on Bond must be filed within 90 days of last furnishing of labor and/or materials to the state job for those who are not working directly with the general contractor in the District of Columbia. Though it is only required for those not contracted directly with the general contractor, it is the best business practice for any supplier to send.
Although it is not a legal requirement to send a preliminary notice for federal projects, it is best practice for subcontractors to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
A Miller Act Notice needs to be sent by subcontractors in 90 days from last furnishing of labor and/or materials to the federal project.
Although it is not a legal requirement to send a preliminary notice, it is best practice to do so for federal projects. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.
A Miller Act Notice is required to be sent by the supplier 90 days from last furnishing of labor and/or materials to the federal project.
Download District of Columbiapreliminary notice, mechanics lien and construction bond claim ebooks and other printable resources
Download District of Columbia preliminary notice, mechanics lien and construction bond claim infographics
Watch and learn from the best of District of Columbia preliminary notice, mechanics lien and construction bond claim videos by SunRay
We have a rich collection of webinar videos that you can stream. Also you can register for our upcoming webinars for free
Stay updated with our blog articles on preliminary notice, notice of intent to lien, mechanic's lien and claim on bond. We cover every update in the lien law in all the 50 states. Subscribe to our newsletter to receive all our updates