Arkansas Lien & Bond Claim Deadlines

What is your project type?
Play Icon
What is your role on the project?
Preliminary Notice
Prior to Furnishing

Pre Construction Notice to Owner (Residential)

For residential projects, a Pre-Construction Notice must be sent before supplying materials to the project.

Lien
120 days from last furnishing

Statement of Account and Claim of Lien

A lien must be filed 120 days from last furnishing labor and/or material. A Notice of Intent to Lien must be sent 10 days before filing a Lien. It is important to leave time to send your intent to lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

Preliminary Notice
Prior to Performing

Pre Construction Notice to Owner (Residential)

For residential projects a Pre-construction Notice must be sent before suppling materials to the project.

Intent to Lien
10 days before Lien

Notice of Intent to Lien

A prerequisite to a lien is a Notice of Intent to Lien, which must be sent 10 days before filing a lien. It is important to leave time to send your Intent to Lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

Lien
120 days from last furnishing

Statement of Account and Claim of Lien

A lien must be filed 120 days from last furnishing labor and/or material. A Notice of Intent to Lien must be sent 10 days before filing a Lien. It is important to leave time to send your intent to lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

Preliminary Notice
Prior to Performing

Pre Construction Notice to Owner (Residential)

For residential projects a Pre-construction Notice must be sent before suppling materials to the project.

Intent to Lien
10 days before Lien

Notice of Intent to Lien

A prerequisite to a lien is a Notice of Intent to Lien, which must be sent 10 days before filing a lien. It is important to leave time to send your Intent to Lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

Lien
120 days from last furnishing

Statement of Account and Claim of Lien

A lien must be filed 120 days from last furnishing labor and/or material. A Notice of Intent to Lien must be sent 10 days before filing a Lien. It is important to leave time to send your intent to lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

What is your role on the project?
Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a preliminary notice, it is best practice to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Lien
120 days from last furnishing

Statement of Account and Claim of Lien

A lien must be filed 120 days from last furnishing labor and/or material. A Notice of Intent to Lien must be sent 10 days before filing a Lien. It is important to leave time to send your intent to lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

Preliminary Notice
Recommended but not required

Preliminary Notice (Commercial Projects)

Although it is not a legal requirement to send a preliminary notice, it is best practice to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Preliminary Notice
75 days from last furnishing

Notice to Owner Notice to Contractor (Commercial)

A Notice to Owner must be sent within 75 days of the last furnishing labor and/or materials.

Lien
120 days from last furnishing

Statement of Account and Claim of Lien

A lien must be filed 120 days from last furnishing labor and/or material. A Notice of Intent to Lien must be sent 10 days before filing a Lien. It is important to leave time to send your intent to lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

Preliminary Notice
Recommended but not required

Preliminary Notice (Commercial Projects)

Although it is not a legal requirement to send a preliminary notice, it is best practice to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Preliminary Notice
75 days from last furnishing

Notice to Owner Notice to Contractor (Commercial)

A Notice to Owner must be sent within 75 days of the last furnishing labor and/or materials.

Intent to Lien
10 days before Lien

Notice of Intent to Lien

A prerequisite to a lien is a Notice of Intent to Lien, which must be sent 10 days before filing a lien. It is important to leave time to send your Intent to Lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

Lien
120 days from last furnishing

Statement of Account and Claim of Lien

A lien must be filed 120 days from last furnishing labor and/or material. A Notice of Intent to Lien must be sent 10 days before filing a Lien. It is important to leave time to send your intent to lien before your 120-day lien deadline passes. For example, if your last day of work was June 30th, the intent to lien must be done by October 18th because the last possible day to file your lien is October 28th.

What is your role on the project?
Statutory Documents are not required for General Contractors
Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a preliminary notice, it is best practice to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Claim on Bond
90 days from last furnishing

Claim on Bond

There is no statutory requirement that a Claim on Bond must be filed. The deadline to sue against the bond is six months.

Claim on Bond
90 days from last furnishing

Claim on Bond

There is no statutory requirement of when a Claim on Bond must be filed, you must look to the bond for the deadline. Generally a bond claim must be filed within 90 days from last furnishing.

The deadline to sue against the bond is six months.

Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a preliminary notice, it is best practice to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

What is your role on the project?
Statutory Documents are not required for General Contractors
Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a preliminary notice for federal projects, it is best practice for subcontractors to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Claim on Bond
90 days from last furnishing

Miller Act Notice

A Miller Act Notice needs to be sent by subcontractors in 90 days from last furnishing of labor and/or materials to the federal project.

Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a preliminary notice, it is best practice to do so for federal projects. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Claim on Bond
90 days from last furnishing

Miller Act Notice

A Miller Act Notice is required to be sent by the supplier 90 days from last furnishing of labor and/or materials to the federal project.

Deadline Calculator
Deadline Calculator
Deadline Calculator
Change State
Deadline Calculator
FAQ's

Learning Center

Don't take our word for it! Trusted by 1000s.

Dots

Don't take our word for it! Trusted by 1000s.

Dots

Florida Lien Law Articles

Stay updated with our blog articles on preliminary notice, notice of intent to lien, mechanic's lien and claim on bond. We cover every update in the lien law in all the 50 states. Subscribe to our newsletter to receive all our updates

More blogs