Oklahoma Lien & Bond Claim Deadlines

What is your project type?
Play Icon
What is your role on the project?
Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a Preliminary Notice, it is best practice to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Lien
4 months from last furnishing

Lien Statement (Original Contractor)

A Lien Statement must be sent 4 months from the last furnishing of labor and/or materials.

Preliminary Notice
30 days from first day on furnishing

Home Owner Notice

A Notice to Owner must be sent by Oklahoma subcontractors on owner-occupied residential properties at the start of work to inform the owners of the possibility of a lien.

Intent to Lien
75 days from last furnishing

Pre-Lien Notice (Intent to Lien)

No pre-lien notice is required if the project is a residential project or is worth $2,500 or less in Oklahoma. In all other cases, it must be sent within 75 days from last furnishing labor and/or materials.

Lien
90 days from last furnishing

Lien Statement (Lower Tier)

A Lien Statement must be sent by the subcontractor to the Kansas commercial job, 90 days from the last furnishing of labor and/or materials.

Preliminary Notice
30 days from first day on furnishing

Home Owner Notice

A Notice to Owner must be sent on owner-occupied residential properties at the start of work by the supplier to inform the owners of the possibility of a lien on their residential project in Oklahoma.

Intent to Lien
75 days from last furnishing

Pre-Lien Notice (Intent to Lien)

No pre-lien notice is required if the Oklahoma project is a residential project or is worth $2,500 or less. In all other cases, it must be sent within 75 days from last furnishing labor and/or materials to the residential project.

Lien
90 days from last furnishing

Lien Statement (Lower Tier)

A Lien Statement must be sent 90 days from the supplier last furnishing labor and/or materials to the residential project in Oklahoma.

What is your role on the project?
Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a Preliminary Notice, it is best practice to do so as a general contractor. Sending a Preliminary Notice advises all parties that you are working on the Oklahoma commercial project and helps you get paid faster.

Lien
4 months from last furnishing

Lien Statement (Original Contractor)

A Lien Statement must be sent by the general contractor to the Oklahoma commercial job 4 months from the last furnishing of labor and/or materials.

Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a Preliminary Notice, it is best practice to do so. Sending a Preliminary Notice advises all parties that you are working on the commercial project and helps you get paid faster as a subcontractor in Oklahoma.

Intent to Lien
75 days from last furnishing

Pre-Lien Notice (Intent to Lien)

No pre-lien notice is required by the subcontractor if the Oklahoma project is a residential one or is worth $2,500 or less. In all other cases, it must be sent within 75 days from last furnishing labor and/or materials.

Lien
90 days from last furnishing

Lien Statement (Lower Tier)

A Lien Statement must be sent 90 days from the subcontractor last furnishing of labor and/or materials to the commercial job.

Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send an Oklahoma Preliminary Notice, it is best practice to do so as a supplier to a commercial job. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.

Intent to Lien
75 days from last furnishing

Pre-Lien Notice (Intent to Lien)

No pre-lien notice is required if the project is a residential project or is worth $2,500 or less. In all other cases, it must be sent within 75 days from last furnishing labor and/or materials to the Oklahoma job by the supplier.

Lien
90 days from last furnishing

Lien Statement (Lower Tier)

A supplier must send a Lien Statement 90 days from the last furnishing of labor and/or materials to the commercial project in Oklahoma.

What is your role on the project?
Statutory Documents are not required for General Contractors
Preliminary Notice
Recommended but not required

Preliminary Notice

Although in Oklahoma it is not a legal requirement to send a Preliminary Notice for state jobs, it is best practice to do so as a subcontractor. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.

Claim on Bond
90 days from last furnishing

Claim on Bond

Subcontractors must send a Lien Statement 90 days from last furnishing labor and/or materials to a commercial project in Oklahoma.

Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a Preliminary Notice in Oklahoma as a supplier, it is best practice to do so for commercial projects. Sending a Preliminary Notice advises all parties that you are working on the project and helps you get paid faster.

Claim on Bond
90 days from last furnishing

Claim on Bond

A Lien Statement must be sent by the supplier 90 days from last furnishing labor and/or materials to the Oklahoma commercial job.

What is your role on the project?
Statutory Documents are not required for General Contractors
Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a preliminary notice for federal projects, it is best practice for subcontractors to do so. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Claim on Bond
90 days from last furnishing

Miller Act Notice

A Miller Act Notice needs to be sent by subcontractors in 90 days from last furnishing of labor and/or materials to the federal project.

Preliminary Notice
Recommended but not required

Preliminary Notice

Although it is not a legal requirement to send a preliminary notice, it is best practice to do so for federal projects. Sending a preliminary notice advises all parties that you are working on the project and helps you get paid faster.

Claim on Bond
90 days from last furnishing

Miller Act Notice

A Miller Act Notice is required to be sent by the supplier 90 days from last furnishing of labor and/or materials to the federal project.

Deadline Calculator
Deadline Calculator
Deadline Calculator
Change State
Deadline Calculator
FAQ's

Learning Center

Don't take our word for it! Trusted by 1000s.

Dots

Don't take our word for it! Trusted by 1000s.

Dots

Oklahoma Lien Law Articles

Stay updated with our blog articles on preliminary notice, notice of intent to lien, mechanic's lien and claim on bond. We cover every update in the lien law in all the 50 states. Subscribe to our newsletter to receive all our updates

No items found.
More blogs